A business battery charges only from the solar panels and does not sell energy.
Today in Cyprus a business battery charges only from your solar panels and powers only the business. It does not charge from the grid and does not sell energy.
The battery changes your connection terms
- When the battery is full: only the solar panels can send energy to the grid. That happens if your connection allows exports.1
- More panels: according to the connection guide of EAC's Distribution System Operator (DSO), a battery can raise the limit for solar from 80% to 100% of the supply's power. This applies to supplies above 3×40 A. For the 100%, the same guide asks for a battery with at least 1 kWh for every kW of solar.2
- Meter and SCADA: if the battery can discharge at 120 kW or more, you fit a separate power meter and link it to the DSO's control room (SCADA).1
- Sensor and technical file: the system needs a direction sensor or a device that controls export. A technical file is also needed, and the DSO's inspectors check it.1
- Adding one later: if you want to add a battery to an existing system, you need a new application and approval from the DSO.2
- Back-up: in a power cut, the battery can keep all or some circuits running. The DSO requires an inverter that works without the grid, an automatic isolation switch and correct earthing.1
The back-up is designed by the electrical engineer. If you want it, it has to be part of the design from the start.1
Connection rules for business solar →
What a home battery is allowed to do →
When the business is closed, the energy left over goes to the grid
The DSO and the Transmission System Operator Cyprus (TSOC) can curtail whenever needed. They can also order zero export, meaning the solar panels stop sending energy to the grid.3
According to the DSO, when a curtailment is for operational reasons, you are not entitled to compensation.1
Since at weekends and on holidays the battery fills up and the rest of the energy goes to the grid, it makes sense to size the battery on what the business uses on working days.
- Occasional zero export: whatever the size of your system, you apply for it in writing to the DSO. Below 120 kW you need a second receiver. From 120 kW upwards the command goes through the DSO's control room.3
- What keeps running: when a zero-export command comes, the solar panels can keep powering whatever machines are running, such as fridges, servers and pumps.3
- Disconnection: even with occasional zero export, the DSO can disconnect the whole system from the grid. Without occasional zero export, the solar panels and the battery are disconnected from the grid together. Whether the battery can meanwhile power the business without the grid is not yet settled.4
How occasional zero export works →
To sell energy you need a separate project
Projects that can sell energy come in two kinds.1
- Solar with storage: the battery charges only from the solar panels and discharges to the grid according to a schedule. Its discharge power cannot exceed the solar's power. You need a licence or exemption from the Cyprus Energy Regulatory Authority (CERA), as well as planning and building permits.1
- Stand-alone battery: it needs a storage licence from CERA.1
Whether such a project can be built at a site that also has its own consumption is not yet settled.
Our calculator for businesses →
Keep reading
If you install solar without a battery in a congested area, you may lose more than half of its output.
In a congested area, new solar usually connects only if it never sends energy to the grid. In the example we worked out, a home without a battery loses 54.3% of its output. See how much the same home saves with a battery.
SolarWith occasional zero export, you can use the power from your solar panels on curtailment days too.
With occasional zero export, a curtailment first stops only your export, and your home can keep using its own solar. You apply in writing to EAC's DSO and pay for the equipment; the DSO can still cut production off.
SolarOn the DSO's map, 21 of Cyprus's 52 areas are congested, so new solar there may not be able to export.
The map of EAC's DSO shows 21 congested areas out of 52, where new solar may connect only with permanent zero export. In our example, without a battery more than half the output is lost.
References
- EAC's DSO, Technical guide for connecting storage systems, edition 2026.3, 15 July 2026, sections 2, 3 and 6. EAC (PDF, in Greek)
- EAC's DSO, Connection guide for active customers and self-consumers, 15 May 2026, sections 4.1 and 4.7. EAC (PDF, in Greek)
- EAC's DSO, Occasional zero export operation, 2025. EAC (PDF, in Greek)
- EAC's DSO, Annex A, special technical and other terms for self-consumption RES, term 21, 2026. EAC (in Greek)
Share
This guide is for information only and is not technical or legal advice. The rules may change. Switch is not responsible for decisions anyone makes based on this guide.